6 - 1 . G e n e r a l R e q u i r e m e n t s . The activity performing the repair is responsible for the performance of all
applicable tests and inspections specified in the technical manuals referenced below. Activities performing
maintenance on any component of the power unit must perform those tests and inspections required by the
applicable component or system repair instruction.
Section
II.
INSPECTION
6-2. G e n e r a t o r
Set
Inspections. Refer to TM 5-6115-465-12 and -34 for inspections required following
6 - 3 . T r a i l e r I n s p e c t i o n s . Refer to TM 9-2330-205-14&P for inspections required following repair of the
trailer.
Section
III.
OPERATIONAL
TESTS
6-4. G e n e r a t o r
Set
Operational
Tests. Refer to TM 5-6115-465-12 and -34 for operational tests required
to verify satisfactory performance of the generator set.
6-5. T r a i l e r O p e r a t i o n a l T e s t s . R e f e r t o T M 9 - 2 3 3 0 - 2 0 5 - 1 4 & P f o r o p e r a t i o n a l t e s t s r e q u i r e d t o v e r i f y
satisfactory performance of the trailer.