ARMY TM 5-6115-633-14&P
CHAPTER 3
OPERATOR/CREW MAINTENANCE INSTRUCTIONS
Section l. CONSUMABLE OPERATING AND MAINTENANCE SUPPLIES
3-1.
Consumable Supplies. Consumable supplies used in the maintenance and operation of the
Table 3-1. Consumable Operating and Maintenance Supplies.
(4)
(2)
(5)
(6)
(3)
(1)
Qty
Qty
required
National
required
for initial
stock
8 hours
Component
number
Description
operation
operation
Notes
application
1 quart
As required
Solvent, Drycleaning,
General
P-D-680
Cleaning
1 pound
As required
Grease, Automotive and
Leg Prop
Artillery, GAA
Assembly
1 quart
As required
Oil, Lubricating,
Leg Prop
OE/HDO-30
Assembly
1 quart
As required
Oil, Lubricating, OEA
Section Il. LUBRICATION INSTRUCTIONS
3-2. General. Detailed instructions for the lubrication of the major components of the power plant are
contained in the applicable Lubrication Orders (LO's). Refer to DA Pam 310-1 to ensure that the latest
editions of the LO's are used.
3-3. Generator Lubrication. Refer to TM
5-6115-585-12 for generator set Lubrication Order.
3-4. Trailer Lubrication. There are no operator/crew lubrication requirements for the power plant
trailer. However, the operator shall assist unit maintenance.
Section Ill. PREVENTIVE MAINTENANCE CHECKS AND SERVICES (PMCS)
NOTE
The PMCS chart in this section contains all necessary Operator/Crew
preventive maintenance checks and services for this equipment.
3-5. General. The preventive maintenance checks and services
listed in
Table 3-2 are grouped
according to stages of equipment operation or time intervals. Using the following as a guide, do the
checks and services at the intervals shown.
a. Before you operate, perform your before (B) PMCS. Observe all CAUTIONS and WARNINGS.
3-1