TM 55-4920-438-13&P
2. As soon as there is enough floor area (4), the
personnel inside will move to the expanded side of the shelter
raising the roof with extended support struts (2).
3. Once the struts (2) are totally supporting
the roof panel (1), the end walls (5) are swung open.
The fold-out floor counterbalance cables must be secured in the cable housings prior to raising
the shelter floor from its lowered position to its level position. If the counterbalance cables are
not secured, the counterbalance cables will remain under tension. DO NOT attempt to remove
cables if the counterbalance cables are not secured. Removing cables while under tension
could cause serious injury to personnel.
4. (For shelter P/N 136-0000-101) Raise the upper lockout
plates (6) on each end wall and install upper lockout pins (7) into
the cable housings.
2-2 Change 1