TM 55-4920-438-13&P
h. Position bar (9) across top of other ECU opening
and install bolts (8).
i. Position bar (10) across bottom of other ECU
opening and install bolts (8).
2-3. Positioning shop equipment. The following procedures and recommended sequence for moving equipment will be
observed. The new positions in which the equipment will be located on the expanded half of the shelter are also
identified.
a. Positioning cabinets, bin storage for operation. Procedures
for moving both cabinets are identical.
1. Remove five bolts (1) from each of the two brackets (2)
located on both sides of the cabinet (3).
2-6 Change 1