TM 55-4920-438-13&P
f. Securing davit crane boom.
1. Swing crane boom (1) under overhead solar
bar (2).
2. Remove strap (3) from storage chest.
3. Loop strap (3) under crane boom (1) and
over solar bar (2). Secure buckle.
Two vises, mounted on the bin
storage cabinets, must be positioned
so that handles are located toward
narrow sides of cabinets. If handles
are pointed in direction of movable
side of shelter they will restrict
closing of the end wall and could
result in damage to the wall.
2-12. Storage procedures. In the event the Power Train
Shop is to be placed in storage the provisions of TM 740-90-1,
TM 743-200-1 and applicable shop equipment TMs will be
followed.
2-13. Striking the shelter. Procedures for striking the shelter
are contained in TM 10-5411-201-14.
In addition, the
following "Supplemental Instructions" will be observed.
a. Remove screws (1) at both corners of fold-out floor.
Change 1 2-29