Table 4-2.
Organizational Troubleshooting (continued)
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION
PSIG PNEUMATIC METER INDICATES PRESSURE (PNEUMATIC POWER SWITCH OFF).
61.
Step 1.
Remove engine access cover. Check visual position indicator on side
a. If valve is fully closed, go to step 5.
b. If valve is not fully closed, continue with step 2.
Step 2.
Shut down engine and set MASTER SWITCH off.
a. If load control valve is now not fully closed, replace valve
b. If valve is now fully closed, continue with next step.
Step 3.
Disconnect main harness connector P4 from ECU. Check for open
a. If circuit is open, reconnect harness connector P4 to ECU and
install control panel. If load control valve is still full
and perform operational check.
b. If circuit is not open, continue with next step.
Step 4.
Test PNEUMATIC POWER switch 1S8 in OFF position (malfunction 79).
b. If switch tests good, check all wires and switches between
pins T and Z of harness connector P4 for shorted condition
c. If switch and wiring is good, replace PSIG PNEUMATIC meter
Step 5.
Test PNEUMATIC POWER switch 1S8 in OFF position (malfunction 79).